Seamester ProgramsSeamester AcademicsDestinationsWhy Seamester?About UsNewsBlogsDates & CostsRequest a Brochure
Home
EnrollmentMy Seamester
FROM CONCEPT TO CREATION: THE BIRTH OF ARGO

After five years of planning, our vision of constructing a custom designed sail training schooner rated for all ocean operations became a reality. Follow the progression of S/Y Argo from computer-aided design to sea trial and find out what it took to create her.

ImageImage


Go To Page 2


February 2005 - Plans, Contracts, and the Beginning of our Global Program

Plans for the construction of our new school-ship S/Y Argo, 112-foot overall staysail schnooner are completed at Langan and Associates in Newport, Rhode Island - home of the drawing boatds for the world's most exclusive sailing yachts. Argo was designed to accomodate 26 students on ocean voyages. The steal for contruction was ordered and plans to build the jib began. Below are some of the plans and first 3-D renderings for the Argo Project.

Image

Above: Starboard side of the vessel showing the general deck arrangement and her lines

Image

Above: General interior arrangement

ImageImage

ImageImage

Above: The thumbnails below are of some recent 3-D renderings of the vessel

 

April 2005 - The Jig is up

We are assigned hull 197 in our shipyard and yard workers begin construction of the Jig, the platform on which the hull will be built.

ImageImage

 

May 2005 - Hull foundations, Framing and Fundamentals

With the Jig completed, construction of Argo's hull begins as the frame is created. Design work in Newport finished up as styling and engineering details are finalized. Check out the progress in the yard and hull renderings by Paul Fuch at Langan Design.

ImageImage
Image

Below: Paul Fuch renderings
ImageImage

June 2005 - Mechanicals and Systems

As construction progressed in the shipyard, we worked hard at ordering all the systerms and equiptment to fill Argo. Below see pictures of the first shipment of systems, including the Caterpillar main engine and the Northern Lights ship's service diesel generators.
ImageImage


July 2005 - Shell Plating

These photos from mid-July truly start to show full hull form. The stern is taking shape and the keel is nearly complete. The propeller aperature framing is now in place and can be seen just aft of where the final engine room frames will be placed.

ImageImage
Image

August 2005 - Turning the Hull Upright

On Friday, August 19th, Argo was pulled out of the covered work area where she was born and rolled right side up! In just six short months she went from the drawing table to looking like a ship. After a few more welds on the shell plating, the fairing stage will begin to smooth out the steal as work on the deck houses, bulwark and interior gets underway.

ImageImage
ImageImage
Image

September 2005 - Building up Deck and Interior

Within a week of the hull being upright, the charthouse was roughed in and the forward deck houses were well underway. Final details were confirmed on the interior fit out and piping and machinery placements are being finalized. The bulwarks were fitted to the deck and with the arrival of the aluminum tube sections from Holland work began to construct the ship's masts. Below are some photos from September.

ImageImage
ImageImage
ImageImage
Image

October 2005 - Welding and Ballast

October saw major gains made in every aspect of the construction. The anchor pockets were installed, along with the lead ballast which was placed in the frame bays of the keel. With the arrival of the first equipment container there were lots of shiny bits ready to be installed. As steel hot work finishes up fairing and painting were set to begin.

ImageImage
ImageImage
ImageImage

November/December 2005 - Painting and Fairing Begin

Work continued and the pace picked up continually. A second shipping container full of gear will be in the yard before year's end. Painting and fairing began on the hull as the spars were built and stainless steel trim was polished and welded in place.

ImageImage
ImageImage
ImageImage
ImageImage
ImageImage

End of 2005 - Buttoning Up

With the conclusion of 2005, the Argo Project was the interior primed and bulkheads installed. The final area of the hull was buttoned up and the cabins started to be test fitted.

ImageImage
ImageImage
ImageImage

Early January 2006 - Picking up the Pace

The shipyard has a full force push to complete the project, and everyday a new part of the puzzle is put into the boat! In every production shop around the shipyard, there are pieces of ARGO nearing completion and waiting to be moved into position.

ImageImage
ImageImage
ImageImage

 

 
Other Programs We Offer
Lifeworks offers service-learning travel programs for teenagers.
ActionQuest offers global adventure programs for teens
P.O. Box 5477
Sarasota, FL 34277 USA
Toll Free 800-317-6789
Tel 941-924-6789
Fax 941-924-6075
Email info@seamester.com
Contact Us Sitemap Request Brochure Apply Now My Seamester Employment